Previous Thread
Next Thread
Print Thread
#486265 02/19/14 04:24 AM
Joined: Oct 1999
Posts: 84,397
Marty Offline OP
OP Offline

The collision of a barge into the pier at Port of Belize Ltd., shortly before five o'clock this morning, has forced the company to temporarily cease operations at the dock.� The freight boat was entering the low berth area of the facility when it crashed into the edge of the wharf, damaging a number of supporting columns beneath.� The vessel, we understand, was coming in from San Pedro when the accident took place.� While the company is looking at an alternate means of loading and offloading cargo from its scheduled arrivals, the owner of the vessel, registered to a company identified only as Crystal, is being investigated by the Belize Ports Authority to determine the cause of the accident.�

Arturo 'Tux' Vasquez, C.E.O., Port of Belize Ltd.

Arturo 'Tux' Vasquez

"We had an incident where one of the barges that comes into the low berth area had ran into the pier.� Damages to the pier is, at this point, it's the beams that support the pier-a portion of the pier not the entire pier-the pier is about a mile long. So those beams will have to be replaced and really that's where the difficulty or I should say the downtime is. We are expecting at this point, anywhere between four to six days to have those beams replaced. Obviously to replace those beams, we will have to take out that portion of the pier which makes the entire pier and everything unusable right now. We have decided not to use the pier head any at all for engineering purposes and safety. So another delay that we will have is that some of the ships that are scheduled to arrive, the agencies, as we speak, are deciding what their options are. It seems that they may decide just to take a delay of a couple of days which means that their cargo may have to go back and come back within a few days. It is obviously safer because an option that we are looking at right now is for the ships that have their cranes on board, we are seeing if it is possible for us to take them�we can dock the cargo ships a little off from the pier and offload them on to barges and then it brings them into the low berth area. But that requires large barges. We have to look at the depth of the low berth area because putting maybe nine forty foot container on a barge sorta needs more draft. So that's what we are looking at right now. And again it is not only us; it is up to the agents to decide whether they need to do that or not. And at this point, there is only one boat that is currently in Cortez that won’t be here until maybe tomorrow. And if they decide still to do that operation then that is something that we will have to orchestrate. For that we need the proper barges which we have, we have them available. And again since the boat has its own crane on board that should be able to work it. But for safety purposes, we will have to consider whether that is the best way to go."

Isani Cayetano

"Has there been an investigation launched to try to understand what transpired last night which resulted in this particular incident?"

Arturo 'Tux' Vasquez

"Yeah, the Belize Port Authority of course was out here first thing this morning. They were also advised and they are the ones that are responsible in looking after the owners of the barge and to make sure that they were under the right captains and procedures that they need to follow up-the licensing of the vessels and all that. So I understand that today they are with the Port Authority providing all of the information. So the Port Authority is the one that does all the investigation when it comes to that. I know the barge is still here at our end. What was on it has been discharged, but I don't think they've allowed them to load anything on and move out. I understand that they are with the Port Authority right now, but again that is for the Port Authority to figure out."

According to C.E.O. Arturo Vasquez, repairs of the damaged pier will cost north of a hundred and fifty thousand dollars.� The work, he says, will be expedited in order to allow for operations to resume at the pier head.

Channel 5


Joined: Oct 1999
Posts: 84,397
Marty Offline OP
OP Offline

Port Remains Closed Until Tuesday

Repairs at the Port of Belize are on schedule, and the port will remain closed until next week Tuesday. CEO Arturo "Tux" Vasquez tells us that the contractor is demolishing the three existing beams that were damaged when the Krystal Tortuga barge ended up underneath the main pier. That's hundreds of feet away from where it should have been on its course to the low-berthing facility. We understand the barge operator is blaming it on a mechanical failure.

Three new beams are scheduled to be put in this weekend and work should be finished by Monday.

In the interim, the arrival of three ships into port have been re-scheduled creating some shipping delays. The damages and delays are expected to cost close to half a million dollars.

Channel 7


Joined: Oct 1999
Posts: 84,397
Marty Offline OP
OP Offline

Port Remains Closed For More Than A Week

Tonight two cargo vessels are waiting at sea and the shelves in the port warehouse are bare because the Port of Belize remains closed, more than a week after a barge crashed into it.

CEO Arturo Vasquez told us this evening that the damaged beams have been removed and hauled away, and work on the news ones has been completed and everything re-assembled. Now, they are waiting for the cement to set so that the bridge can reach the required strength to support the massive weight of containers being hauled across it.

Work to cast the three beams that had to be replaced finished at 3:30 this morning - and the cement needs 24 hours to reach the required strength. So that should be finished at 3:30 tomorrow morning - in time for offloading of the Seaboard vessel to start at 8:00 am.

Vasquez says the Seaboard will be brought into dock tonight, so that it is ready for tomorrow morning. After that, the Palencia which has been waiting for four days to offload will get its turn.

But, this schedule depends on the outcome of a concrete stress test which is planned for tomorrow morning at 7:00,. Only if the concrete passes that test, will the bridge be cleared for heavy traffic.

The week of closure has seriously affected merchants, exporters and shipping agents. It was caused by an accident where the Krystal Tortuga barge crashed into the bridge last Tuesday morning.

Channel 7


Joined: Oct 1999
Posts: 84,397
Marty Offline OP
OP Offline

Repairs near completion on Port of Belize's pier

Repairs to the wharf at Port of Belize Ltd. have been ongoing since an accident last Tuesday during which an incoming barge caused significant structural damages when it collided into the supporting columns below the pier.� New beams, we are told, were successfully installed on Monday and tonight finishing works are underway.� The pier should be partially operational by eight o'clock, once all the gratings, waterline and electrical lines have been restored.� Light trucks will only be allowed unto the quay in the interim, as it is expected that a team of engineers will conduct final assessments of the required PSI necessary on Wednesday morning.� In the interest of saving time a Seaboard vessel, complete with all necessary boarding processes, will be the only freighter allowed to dock tonight.� Operations on that vessel are scheduled to begin in the morning.� That decision was taken as a result of the Wednesday's cruise ship schedule.

Channel 5



Link Copied to Clipboard
March
S M T W T F S
1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30
31
Cayo Espanto
Click for Cayo Espanto, and have your own private island
More Links
Click for exciting and adventurous tours of Belize with Katie Valk!
Who's Online Now
0 members (), 306 guests, and 0 robots.
Key: Admin, Global Mod, Mod
Forum Statistics
Forums44
Topics79,199
Posts500,011
Members20,460
Most Online7,413
Nov 7th, 2021



AmbergrisCaye.com CayeCaulker.org HELP! Visitor Center Goods & Services San Pedro Town
BelizeSearch.com Message Board Lodging Diving Fishing Things to Do History
BelizeNews.com Maps Phonebook Belize Business Directory
BelizeCards.com Picture of the Day

The opinions and views expressed on this board are the subjective opinions of Ambergris Caye Message Board members
and not of the Ambergris Caye Message Board its affiliates, or its employees.

Powered by UBB.threads™ PHP Forum Software 7.7.5